Bunkering
Precautions, including Bunkering Checklist
1. The Master of the ship
involved in bunkering shall ensure that bunkering will only take place if:
a. notification of the
intention to bunker is given to the port authority well in advance, stating the
place, type of bunker, oil to be transhipped and the expected time that
bunkering will commence and
b. the questions on the
attached bunkering checklist are answered truthfully and affirmatively.
2. The Master of the ship
shall not begin bunkering unless he has ensured that:
a. the scuppers are firmly
closed
b. bunker pipes which are
not in use are well blanked
c. the bunker hoses are
properly supported
d. the bunker hoses have
sufficient play
e. the bunker connection
has been provided with a good seal
f.
there
is a well-tightened bolt in every bolt hole in the bunker pipe connection
flanges
g. there is a sufficiently
large overflow basin under the bunker pipe connection (s) and
h. any cargo handling
operations in progress will not hazard the bunker operations
3. The Master of a bunker
vessel shall not begin bunkering unless he has ensured that:
a. the bunker vessel is
securely moored
b. the bunker hoses are in
good condition
c. the bunker hoses have
sufficient play
d. the bunker connection
has been provided with a good seal and
e. there is a well
tightened bolt in every bolt hole of the bunker pipe connection flanges
4. The Master of a ship
involved in bunkering shall ensure that the conditions described in paragraphs
2 and 3 remain fulfilled during the entire bunkering procedure
5. Both, the Master of a
ship and the Master of a bunker vessel should ensure, that a constant visual
watch is maintained throughout the whole transfer operation
6. Both, the Master of a
ship and the Master of a bunker vessel have to ensure that all scuppers are
closed and that sufficient absorbing materials are available in case of an
accidental spillage.
7. If it cannot be ensured
during the whole bunkering operation that the requirements laid down in this
annex are fulfilled, the Master of the ship and/or the bunker vessel shall
cease the bunker operation immediately.
8. In this annex, bunkering
is taken to mean the transfer of bunker oil, that is a flammable liquid
intended for the propulsion and or the auxiliary operation of a ship or liquid
intended for lubricating the ship’s engine or her other machinery.
The Chief Officer and the Chief Engineer in
co-operation shall ensure that: the above is complied with, including
completion of the Pre-transfer Bunker Checklist.
The Chief Engineer shall ensure that:
a. all self closing devices
on sounding pipes to double bottom tanks in the engine room and shaft tunnel
operate correctly and easily.
b. the self closing devices
on sounding pipes are closed after use.
c. prior to bunkering the
double bottom air pipes are in order. This includes checking that the safety
gauze is not blocked with paint thus reducing the air flow. Where Bolaco valves
are fitted, they shall be checked for free movement.
d. heavy fuel oil vapours
are measured for Hydrogen Sulphide (H2S
detector preferably on board the barge.
The acceptance level of
H2S in the tank atmosphere is up to 200 ppm. If H2S in the tank atmosphere is
found in excess of 200 PPM, the fuel should be rejected and the parties in
charge of vessel’s bunker supply notified accordingly.
H2S can be detected by
various means of portable measuring equipment.
The TLV limit for H2S is
5ppm. Thus, if carrying bunkers with high H2S readings, it is required that
personnel working directly with the fuel oil, e.g. when cleaning filters,
measure for H2S at the working site and observe safe working practices by
having sufficient ventilation - if necessary by rigging an extra ventilator.
e. the filling rate in an
individual branch line does not exceed 2m/sec. Applicable filling rates for
different diameter pipes are:
Nominal pipe diameter
(mm) 100 125 150 200 250 300 350 400
Rate (m3/h)
63 97
144 243 383 548 652 855
If for example three
tanks are filled simultaneously each with 100mm filling line, then a maximum
rate of 3 x 63 = 189 m3/h should be ordered. The rate should be reduced
proportionally as the number of tanks to fill decrease and when the final tank
is being topped off, the flow rate should be further reduced to allow more time
for the distribution of the oil when its level is above the holes in the floors
and intercostals.
bunkering is not
started:
·
until
the Chief Officer has confirmed that the above point 2.1 through 2.8 are
complied with
·
the
Chief Officer has provided an abundant supply of absorbent material at the
bunkering manifold
·
the
Chief Officer has prepared the fire fighting equipment for immediate use
·
watch
personnel are appointed for constant monitoring of the manifold, the hose, the
bunker barge moorings and the tanks being filled.
·
the
bunker supplier’s representative is present and able to stop the bunkering
instantly.
Pre Bunkering Plan
The pre-bunkering plan
shall be prepared prior to the training session and a copy of the plan shall be
posted at a location where it is easily observed by the personnel engaged in
the bunkering.
The pre-loading plan
must include:
- Identification,
location and capacity of the vessel’s bunker tanks receiving oil.
- Level
and type of liquid in each bunker tank prior to the scheduled time for
bunkering.
- Final
ullage and percent of each bunker tank to be filled.
- Sequence
in which the bunker tanks are to be filled.
- Procedure
to regularly monitor all bunker tank levels and valve alignments.
Pre Bunker Meeting
All precautions to
prevent pollution during bunker loading transfer and discharging shall be taken
and the precautions shall be planned during the Pre Bunker meeting. The
preplanning meeting shall be recorded.
The Master and the Chief
Engineer shall ensure during the Pre Bunker meeting that personnel involved in
bunker transfer are familiar with all precautions to be taken.
Vessels personnel shall
furthermore be familiar with the Spill Contingency Procedures and facilities as
outlined in the vessels’ Oil Pollution Emergency Plan (SOPEP/SMPEP) and the
applicable local requirements for the bunkering.
Pre Bunkering Training
Within 48 hours prior
the bunkering / bunker transfer operation a bunkering training session must be
conducted. The training session shall be for all personnel with duties related
to the bunker transfer.
The training shall
include:
• The pre-bunkering
plan.
• Civil/criminal
penalties and liabilities.
• Vessels Oil Transfer
Procedure.
• English phrases and
hand signals for communication.
• Emergency shutdown
procedures.
Date and time of the
bunker training session shall be recorded in the deck log along with name and
rating of all persons attending the bunker training session.
Tidak ada komentar:
Posting Komentar